Milestone Burnup

Not available in Agile Central On-Premises.

The milestone burnup chart shows how work is tracking to the target date. The blue line indicates scope, and the green bars are the accepted work on a given date.

From the Burnup chart Settings, you can select the count of user stories and defects instead of points, or you can select to view both points and count.

Note: The first story points are not the complete picture of the number of points in a milestone. The Burnup Chart includes a total number of points for user stories and defects associated to them regardless of what milestone the defects are associated to. The chart counts all defects which are associated to the user stories as well, even if they are not associated to the same milestone.

Milestone Burnup, points or count